Articolo 90Termination of contracts
In vigore · versione del 1 gen 2026
Member States shall ensure that contracting entities have the possibility, at least under the following circumstances and under the conditions determined by the applicable national law, to terminate a works, supply or service contract during its term, where:
(a) the contract has been subject to a substantial modification which would have required a new procurement procedure pursuant to Article 89;
(b) the contractor has, at the time of contract award, been in one of the situations referred to in Article 57(1) of Directive 2014/24/EU and should therefore have been excluded from the procurement procedure pursuant to the second subparagraph of Article 80(1) of this Directive;
(c) the contract should not have been awarded to the contractor in view of a serious infringement of the obligations under the Treaties and this Directive that has been declared by the Court of Justice of the European Union in a procedure under Article 258 TFEU.