Commission Implementing Regulation (EU) 2016/545 of 7 April 2016 on procedures and criteria concerning framework agreements for the allocation of rail infrastructure capacity (Text with EEA relevance)
Articolo 9Coordination in case of conflicting requests for framework agreements for any time after the end of the next timetable period
In vigore · versione del 28 apr 2016
1. If the infrastructure manager encounters conflicts between existing framework agreements and requests for new or modified framework agreements or between requests for new framework agreements, the principles of the coordination procedure for path requests provided for by Article 46(3) and (4) of Directive 2012/34/EU shall apply.
2. The infrastructure manager shall attempt through the first coordination to ensure the best possible matching of the conflicting requests or of a request and existing framework agreements.
3. Where existing framework agreements and requests for new framework agreements or requests to modify agreements cannot be reconciled after a first coordination round, following the rejection by the interested parties of the solution proposed by the infrastructure manager, the latter shall assess those requests and, if relevant, existing framework agreements, taking into account the criteria provided in Article 10(2) to (4).
4. On the basis of the assessment in accordance with paragraph 3, the infrastructure manager shall perform a second round of coordination. If the second coordination round has proven unsuccessful and if the requested framework agreement provides for making a better use of the infrastructure, the infrastructure manager shall request the modification of framework capacity allocated under existing framework agreements.
5. If the second coordination round has proven unsuccessful and if a requested framework agreement does not provide for making a better use of the infrastructure than one or several existing conflicting framework agreements, the infrastructure manager shall reject the request.
6. The infrastructure manager may reject a requested framework agreement, if the additional income generated from concluding the new framework agreement would not at least offset possible penalties, as referred to in Article 13, pursuant to the modification referred to in paragraph 4 of this Article.
7. If it is not possible to satisfy requests for framework agreements for reasons of actual or expected lack of infrastructure capacity, the infrastructure manager may declare the section of infrastructure concerned to be congested in accordance with Article 47 of Directive 2012/34/EU.