Commission Implementing Regulation (EU) 2016/545 of 7 April 2016 on procedures and criteria concerning framework agreements for the allocation of rail infrastructure capacity (Text with EEA relevance)
Article 8Ceilings for the allocation of framework capacity
In force · version of Apr 28, 2016
1. The infrastructure manager shall divide each 24 hour period into control periods of no longer than two hours each. When allocating framework capacity the infrastructure manager shall assign the time frames to control periods.
2. Where the infrastructure manager allocates framework capacity of not more than 70 % of the maximum capacity in any given control period on a line, it may decide not to apply Article 9(3) to (6), Article 10 and Article 11(1) as regards those control periods. The maximum capacity shall be calculated on the basis of existing and planned headways of trains and the estimated number of trains on the line concerned. The infrastructure manager shall publish in the network statement its methodology for calculating the maximum capacity for the purpose of this paragraph.
3. Where prior approval of framework agreements by the regulatory body in accordance with the second subparagraph of Article 42(1) of Directive 2012/34/EU is required, a Member State may decide not to apply any or all of paragraph 2 and Articles 9(3) to (6) and 10.