Commission Implementing Regulation (EU) 2018/2067 of 19 December 2018 on the verification of data and on the accreditation of verifiers pursuant to Directive 2003/87/EC of the European Parliament and of the Council (Text with EEA relevance.)
Article 17bChecking the application of derogations listed in Article 22a(1), second subparagraph, of Delegated Regulation (EU) 2019/331
In force · version of Jun 22, 2025
1. Where the implementation of recommendations referred to in Article 17a of this Regulation has not been completed, the verifier shall assess the operator’s evidence and check whether: (a) the energy efficiency recommendations referred to in Article 22a(1), second subparagraph, point (f), of Delegated Regulation (EU) 2019/331 were not issued in the first four years of the baseline period; (b) recommendations would not lead to energy savings within the system boundaries of the industrial process carried out at the installation; (c) the pay-back time referred to in Article 22a(1), second subparagraph, point (a), of Delegated Regulation (EU) 2019/331 exceeds three years; (d) the installation specific operating conditions, including planned or unplanned periods of maintenance, upon which the pay-back period was determined have not yet occurred; (e) the investment costs of the recommendations exceed the thresholds listed in Article 22a(1), second subparagraph, point (b) of Delegated Regulation (EU) 2019/331; (f) other measures have been implemented during or after the relevant baseline period which led to greenhouse gas emission reductions equivalent to those recommended by the energy audit report or a certified energy management system for the installation.
2. Where the pay-back time referred to in Article 22a(1), second subparagraph, point (a), of Delegated Regulation (EU) 2019/331 is not specified in the energy audit report, the certified energy management system or a sworn declaration from the energy auditor, the verifier shall check: (a) the validity of the information used to determine the pay-back time; (b) the correct application of the method used to determine the pay-back time.
3. For the purpose of assessing implementation of measures referred to in paragraph 1, point (f), the verifier shall check and confirm whether: (a) the operator has implemented the alternative measures and whether the implementation of those measures has been completed; (b) equivalent greenhouse gas emission reductions referred to in paragraph 1, point (f), have been achieved.