Commission Implementing Regulation (EU) 2026/256 of 30 January 2026 on data reporting implementing Article 7c(2), Article 8(1a), Article 8(2) and Article 8(6) of Regulation (EU) No 1227/2011 of the European Parliament and of the Council on wholesale energy market integrity and transparency and repealing Commission Implementing Regulation (EU) No 1348/2014
Article 2Definitions
In force · version of Apr 29, 2026
For the purpose of this Regulation, the following definitions shall apply:
(1) ‘fundamental data’ means information related to the capacity and use of facilities for production, storage, consumption or transmission of electricity and natural gas or related to the capacity and use of LNG facilities, including planned or unplanned unavailability of such facilities;
(2) ‘standard contract’ means a contract concerning a wholesale energy product that is admitted to trading at an OMP;
(3) ‘non-standard contract’ means a contract concerning any wholesale energy product that is not admitted to trading at an OMP;
(4) ‘group’ means group as defined in Article 2, point (11), of Directive 2013/34/EU of the European Parliament and of the Council ( 7 ) ;
(5) ‘intragroup transaction’ means a transaction relating to wholesale energy products entered into with a counterparty which is part of the same group provided that both counterparties are included in the same consolidation on a full basis;
(6) ‘over-the-counter’ or ‘OTC’ means any transaction carried out outside an organised marketplace;
(7) ‘nomination’ means: (a) for electricity, the notification of the use of cross zonal capacity by a physical transmission rights holder and its counterparty to the respective Transmission System Operators; (b) for natural gas, the prior reporting by the network user to the Transmission System Operator of the actual flow that the network user wishes to inject into or withdraw from the system;
(8) ‘balancing energy’ means energy used by transmission system operators to carry out balancing;
(9) ‘balancing capacity’ means a volume of capacity that a balancing service provider has agreed to hold and in respect to which the balancing service provider has agreed to submit bids for a corresponding volume of balancing energy to the transmission system operator for the duration of the contract;
(10) ‘balancing service’ means: (a) for electricity, a service provided to a Transmission System Operator consisting of the provision of either balancing capacity or balancing energy or both balancing capacity and balancing energy; (b) for natural gas, a service provided to a Transmission System Operator to meet short term fluctuations in natural gas demand or supply;
(11) ‘consumption unit’ means a resource which receives electricity, natural gas or hydrogen for its own use;
(12) ‘production unit’ means a facility for generation of electricity made up of a single generation unit or of an aggregation of generation units;
(13) ‘balance responsible parties’ shall have the same meaning as in Article 2 of Regulation (EU) 2019/943 of the European Parliament and of the Council ( 8 ) ;
(14) ‘transaction’ means any trade and order to trade, matched or unmatched, or bilateral contract and its execution related to wholesale energy products, including any lifecycle event of such trade, order to trade or bilateral contract;
(15) ‘lifecycle event’ means any modification, cancellation, correction, early termination or, where applicable, execution of any trade, order to trade, matched or unmatched, or bilateral contract related to wholesale energy products;
(16) ‘trade-matching system’ means a system that facilitates the matching of orders to trade in wholesale energy products and where the conclusion of the transaction takes place outside of the trade-matching system;
(17) ‘storage facility’ means: (a) for electricity, energy storage facility as defined in Article 2, point (60), of Directive (EU) 2019/944 of the European Parliament and of the Council ( 9 ) ; (b) for natural gas, natural gas storage facility as defined in Article 2, point (31), of Directive (EU) 2024/1788 of the European Parliament and of the Council ( 10 ) ;
(18) ‘entry-exit system’ means entry-exit system as defined in Article 2, point (57), of Directive (EU) 2024/1788;
(19) ‘capacity mechanism’ means capacity mechanism as defined in Article 2, point (22), of Regulation (EU) 2019/943;
(20) ‘renewable hydrogen’ means hydrogen qualifying as biogas as defined in Article 2, point (28), of Directive (EU) 2018/2001 of the European Parliament and of the Council ( 11 ) , and hydrogen qualifying as renewable fuels of non-biological origin as defined in Article 2, point (36), of that Directive;
(21) ‘low-carbon hydrogen’ means low-carbon hydrogen as defined in Article 2, point (11), of Directive (EU) 2024/1788;
(22) ‘redispatching’ means redispatching as defined in Article 2, point (26), of Regulation (EU) 2019/943;
(23) ‘contracts-for-difference’ means contracts for difference as defined in Article 2, point (76), of Regulation (EU) 2019/943.